Confidential Data Centre E1

12MW extension to an existing data centre site in Slough

The design provided the flexibility for Hot or cold Aisle containment,  distributed redundant power to PDU’s / RPP’s, Hybrid Dry Air Coolers with Trim Adiabatic Air Cooled Chillers and CRAH’s to the data halls.

Desco carried out a Peer review of the Stage 3 Design and Stage 4A design duties across the majority of services in the facility.

 

Location

London

White Space

6,600m2

IT Capacity

12MW

Year

2020/21